Welcome to our team web site for informatics 117! This is where you will be able to track the updates on our project, view our calendar of deadlines, and contact us. You will also be able to

read summaries of our meetings right here on the main page.

 

 

Our weekly meeting times are as follows:

  • Tue (5:00 PM – 6:00 PM)
  • Wed (5:45 PM – 7:00 PM)
  • Fri (3:30 PM – 5:30 PM) - Meet with client

 

Our showcase events with our client:

  • Fri, Feb 21 (3:30 PM – 4:45 PM)
  • Tue, Feb 26 (5:00 PM – 6:00 PM)
  • Tues, Mar 11 (5:00 PM – 6:00 PM)

 

Delivery of final product:

  • Fri, Mar 14 at 3:30pm
u p d a t e s

Updates on March 13, 2008

  • Test plan iteration 3 is up which includes all tests - unit, integration, acceptance - and all of their results.
  • Requirements and Design document have been updated for the final delivery

 

Updates on March 2, 2008

  • Code Iteration 3 is up. Iteration 3 is version 1.8.4. This is the 27th version.
  • team log #2 is up.

 

 

Updates on February 25, 2008

  • Code Iteration 2 is up. Iteration 2 is version 1.7.4.2. This is the 19th version.

 

Updates on February 22, 2008

  • Emergency Meeting with the client. Client had a lot of valuable feedback regarding Design Doc 4.
  • This meeting was also used to showcase our work thus far to the client. He seemed relatively pleased with the code progress and again had much valuable and important feedback regarding future changes.

 

Updates as of February 20, 2008

  • After making corrections with out client, Design Doc Iteration 4 is up! 
  • Acceptance Tests have been updated
  • Corrected the old naming problems, redid a few diagrams, and added details for all of the classes.

 

Updates as of February 19, 2008

  • Project Plan 3 is complete
  • Design Doc 2 has undergone major changes and is now posted as Iteration 3
  • Integration Tests are posted (Test Plan 2)
  • Implementation Iteration 1 uploaded

 

Updizzles for Feb the Five, Two-Dub'lo-Eight

  • Requirements Final Draft (hopefully) is posted (and updated a bit)
  • Pre-Alpha prototype is on the discussion board
  • Project Plan #2 uploaded

 

Updates on January 31, 2008

  • Test Scenarios added to Acceptance Tests.
  • Sequence Diagrams created.

 

 

Uploads on January 28, 2008

 

  • Test Plan has been updated slightly 1/28 10am.
  • Test Plan and Requirement iteration #2 are up.

    please check the deliverable sections for these documents.

    Thank you for your effort and time this weekend.  see you tomorrow in class :)
     

Meeting with Reazon on January 25, 2008

 

  • The second meeting recording is ready for download. If you have problem downloading it, please call me.
  • Address the type errors and misidentified requirements and revise them.
  • Test Plan.
  • Refine 2nd iteration requirement. 
  • Have a good weekend :)

 

Meeting with Reazon on January 18, 2008

 

  • We met with Ramesh from Reazon to gain a better understanding of our project. We met at their office in Santa Ana where we were able to interview Ramesh and have him explain the overview of the project. To view the write up of this meeting, click here (PDF).

 


 

 

 